RPA03-North and South County Trailway Infrastructure
- Construction of North County Trailway from Eastview to Putnam County line complete. Construction of South County Trailway from Route119 to Barney Street complete.
RTB05-Tibbetts Brook Park Infrastructure
- Construction underway for repaving of pathways and roadways, storm drainage, parking improvements and planting.
RWPR4-Ward Pound Ridge Reservation Dam Project
- Design for improvements to the spillways and riverbanks complete. Construction to begin.
RWW04-Willson’s Woods Lake Rehabilitation
- Design for rehabilitation of the area including a perimeter path and pavilion underway.
RP02A-Playland Ice Casino Improvements II
- Design of building improvements are underway.
RP006-Playland Various Rides and Components
- Rehabilitation of the historic Grand Carousel and Derby Racer Pavilions construction complete.